The resources committed to the project allowed plans put forward by the League engineer Rhiner Van Hesselman to be implemented. The | The resources committed to the project allowed plans put forward by the League engineer Rhiner Van Hesselman to be implemented. The defenses of Holberg were repaired to pre-siege levels, despite the fact that the territory was not under Imperial control at the time. | ||
[[Category: Senate Motion]] | [[Category: Senate Motion]] | ||
[[Category: 377YE Spring]] | [[Category: 377YE Spring]] |
Revision as of 17:01, 22 January 2022
To build defenses at Holberg
Proposed by Necropolis, seconded by Karov
Proposed by Necropolis, seconded by Karov
Overview
- Perform emergency repair of the gates and walls of Holberg based on plans presented to the League by the engineer Rhiner Van Hesselman.
- Passed at 45 Thrones with 13 votes against
- Funds disbursed to Adamah of the Silent tide, Senator for Necropolis.
Date
- Spring 377YE
Cost
- 100 crowns
- 25 wains white granite
- 10 wains weirwood
- 25 measures of Bladeroot
- 25 measures of Imperial Roseweald.
Progress
- Paid by Oksana Kazaku, senator for Temeschwar in Spring Equinox downtime
Campaign Outcome
- Walls of Holberg restored to full strength.
The resources committed to the project allowed plans put forward by the League engineer Rhiner Van Hesselman to be implemented. The defenses of Holberg were repaired to pre-siege levels, despite the fact that the territory was not under Imperial control at the time.